This project started in early October 2011. It was an Engineering topographic survey of 5.2 km of Highway 2 with a site plan at its crossing of Tupper Creek.
#2-2232 Wilgress Rd. Nanaimo, BC V9S 4N4 | Telephone: 250.756.4500 | Email: info@3dgeomatics.com
This project started in early October 2011. It was an Engineering topographic survey of 5.2 km of Highway 2 with a site plan at its crossing of Tupper Creek.
We began by integrating existing BC MoT control survey with in required survey area. Once we had set required control we set QC points to check into during the topographic survey. We surveyed the road surface out to the back of ditches, and areas and features that would not show up in the existing LiDAR data set. Our field survey was integrated in with the existing LiDAR survey to create a robust hybrid of wide reaching LiDAR and very accurate road right of way topology.
Plans production for this project included creating an up-to-date legal fabric and compiling an underground utility network, for both the roadway and the creek site plan. Terrain profiles and Cross sections of the roadway and creek were struck and recorded as part of the plan set deliverables.
Field work was completed in early October and project deliverables submitted at the end of November 2011.